A ruling that a contracting party's delay in performing the obligation because the other contracting party ceased paying the amounts due for previous operations does not constitute fault. Correct.
Arabic original
القضاء بأن تراخي المتعاقد عن تنفيذ الالتزام لتوقف المتعاقد الآخر عن الوفاء بالمستحقات عن العمليات السابقة لا يشكل خطأ. صحيح.Original Arabic judgment citations
(الطعن ١٩٢/٨٤ تجاري جلسة ٢٤/٤/١٩٨٥ مج القسم الأول - المجلد الثاني ص ٦٠٣)
Source: Court of Cassation legal principles collection — Civil Matters — Volume 10 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 315. PDF pages: 315.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- أثر العقد. عدم إنصرافه إلا إلى عاقديه وخلفهما العام. التعامل مع المتجر ككيان ينظر فيه إلى عنوانه التجاري دون ا…
- استخلاص الخطأ. واقع. يستقل بتقديره قاضي الموضوع ما دام سائغاً.…
- وصف الفعل بأنه خطأ أو غير خطأ. مسألة قانونية. أما استخلاص توافر الخطأ أو نفيه فمسألة واقع يدخل في سلطة محكمة ا…
- كل فعل خاطىء يولد المسئولية عن الخسارة التي وقعت والكسب الذي فات. شرط ذلك. أن يكونا نتيجة طبيعية للفعل ولم يكن…
- استخلاص الخطأ الموجب للمسئولية وتقدير توافر الضرر وعلاقة السببية بينهما. واقع تستقل به محكمة الموضوع. شرط ذلك.…
- انتهاء الحكم في حدود سلطته التقديرية إلى أن تقصير الطاعن في التوريد هو السبب في وقوع الضرر. الجدل في ذلك. موضو…