Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 2325

State of Kuwait · Civil Matters — Volume 10 · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

An increase or decrease in the costs of the work. Has no effect on the extent of the obligations arising under the contract for works: the contractor may not, upon an increase in costs, demand an increase in the consideration, nor may the employer, upon a decrease in costs, demand a reduction in the consideration. Its condition. Without prejudice to the provisions of the doctrine of unforeseen circumstances. - The contractor’s obligation, if factors arise during performance of the work that could impede performance, to notify the employer immediately; otherwise, he is liable for everything resulting therefrom.
Arabic original
ارتفاع تكاليف العمل أو انخفاضها. لا أثر لها في مدى الالتزامات التي يرتبها عقد المقاولة: لا يجوز للمقاول عند ارتفاع التكاليف المطالبة بزيادة في المقابل ولا يجوز لصاحب العمل عند انخفاض التكاليف المطالبة بإنقاص المقابل. شرطه. عدم الإخلال بأحكام نظرية الظروف الطارئة. - التزام المقاول إذا قامت عوامل أثناء تنفيذ العمل من شأنها أن تعوق التنفيذ بإخطار رب العمل فوراً وإلا كان مسئولاً عن كل ما يترتب على ذلك.
Original Arabic judgment citations

(الطعن ٢٢٥/١٩٩٠ تجاري جلسة ١٥/٣/١٩٩٢ مج القسم الثالث - المجلد الثالث ص ١٦٢)

Source: Court of Cassation legal principles collection — Civil Matters — Volume 10 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 431. PDF pages: 431.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace