Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 283

State of Kuwait · Civil Matters — Volume 11 · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

Termination of the contract for works due to impossibility of performance for a reason beyond either party's control. Its effect. Both parties' obligations are extinguished and the contract for works is automatically rescinded, and the contractor is entitled to compensation under the principle of unjust enrichment, thus obtaining from the employer compensation equal to his expenditure and the remuneration due to him, within the limits of the benefit accruing to the employer.
Arabic original
انتهاء المقاولة باستحالة التنفيذ لسبب لا يد لأحد الطرفين فيه. أثره. انقضاء التزام الطرفين ويفسخ عقد المقارلة من تلقاء نفسه ويستحق المقاول تعويضاً بموجب مبدأ الإثراء بلا سبب فيقتضى تعويضاً من صاحب العمل قيمته ما أنفقه وما يستحقه من أجر في حدود ما عاد من منفعة على صاحب العمل.
Original Arabic judgment citations

(الطعن ١٠٩٦/٢٠٠٤ إداري جلسة ٢٤/١/٢٠٠٦ مج القسم الخامس - المجلد الرابع ص ٤٧٣)

Source: Court of Cassation legal principles collection — Civil Matters — Volume 11 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 65. PDF pages: 65.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace