Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 2615

State of Kuwait · Commercial and Labour — Volume 9 · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

An increase or decrease in the costs of the work. It has no effect on the extent of the obligations created by the works contract. The contractor may not demand an increase in the consideration when costs rise, nor may the employer demand a reduction in the consideration when costs fall. Its condition. Without prejudice to the provisions of the doctrine of unforeseen circumstances. - The contractor's obligation, if factors arise during performance of the work that may impede performance, to notify the employer immediately; otherwise, he is liable for everything resulting therefrom.
Arabic original
ارتفاع تكاليف العمل أو انخفاضها. لا أثر لها في مدى الالتزامات التي يرتبها عقد المقاولة. لا يجوز للمقاول عند ارتفاع التكاليف المطالبة بزيادة في المقابل ولا يجوز لصاحب العمل عند انخفاض التكاليف المطالبة بإنقاص المقابل. شرطه. عدم الإخلال بأحكام نظرية الظروف الطارئة. - التزام المقاول إذا قامت عوامل أثناء تنفيذ العمل من شأنها أن تعوق التنفيذ بإخطار رب العمل فوراً وإلا كان مسئولاً عن كل ما يترتب على ذلك.
Original Arabic judgment citations

(الطعن ٢٢٥/١٩٩٠ تجاري جلسة ١٥/٣/١٩٩٢ مج القسم الثالث - المجلد الثالث ص ٣١٢)

Source: Court of Cassation legal principles collection — Commercial and Labour — Volume 9 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 449. PDF pages: 449.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace