Kuwait Court of Cassation principle number 2490
State of Kuwait · Civil Matters — Volume 10 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
The seller's failure to perform its obligation to deliver the thing sold at the specified time. Its effect. The contract is deemed rescinded unless the buyer notifies the seller that it insists on performance of the contract.
Arabic original
عدم تنفيذ البائع لالتزامه بتسليم المبيع في الموعد المحدد. أثره. اعتبار العقد مفسوخاً إلا إذا أخطر المشتري البائع بتمسكه بتنفيذ العقد.Original Arabic judgment citations
(الطعن ٢١٢/٩٢ تجاري جلسة ١٦/٦/١٩٩٣ مج القسم الثالث - المجلد الثالث ص ٣٩١)
Source: Court of Cassation legal principles collection — Civil Matters — Volume 10 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 460. PDF pages: 460.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- القسائم الصناعية المملوكة للدولة. لا تعتبر مالاً عاماً إنما من أموال الدولة الخاصة. أثر ذلك: موافقة الدولة على…
- فسخ العقود الملزمة للجانبين. لا يكون إلا بحكم قضائي أو باتفاق الطرفين. للقاضي الاستجابة لطلب الفسخ أو رفضه حسب…
- أثر فسخ العقد أو انفساخه. إعادة الحال إلى ما كانت عليه قبل العقد.…
- تقدير التعويض عن فسخ عقد العمل محدد المدة. من سلطة محكمة الموضوع ما دامت قد التزمت الضوابط المنصوص عليها في ال…
- فسخ عقد البيع نتيجة بيع البائع للعقار المبيع يجعل البائع مسؤولاً عن تعويض المشتري طبفاً لقواعد المسئولية التقص…
- مجال الرجوع إلى أحكام البيع في القانون المدنى بالنسبة لعقد المقاولة ينحصر في نطاق ما إذا وجد عيب في مواد العمل…