Kuwait Court of Cassation principle number 3478
State of Kuwait · Civil Matters — Volume 11 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
Determining the existence or absence of fault by the employer or the main contractor in his capacity as employer, by which the contractor's liability for delay in performance is removed. Falls within the authority of the court of merits. The condition for this. An example.
Arabic original
استخلاص توافر خطأ رب العمل أو المقاول الأصلي بوصفه رب عمل الذي ترتفع به مسئولية المقاول عن التأخير في التنفيذ أو نفيه. من سلطة محكمة الموضوع. شرط ذلك. مثال.Original Arabic judgment citations
(الطعن ٣٠٦/٩٥ تجاري جلسة ١٠/٣/١٩٩٧ مج القسم الرابع - المجلد السادس ص ٥٢٠)
Source: Court of Cassation legal principles collection — Civil Matters — Volume 11 — Ministry of Justice — Court of Cassation — Technical Office. PDF pages: 685.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- التزام المستأجر ببذل عناية الشخص العادي في استعمال المأجور والمحافظة عليه ورده بالحالة التي تسلمه عليها إلا ما…
- فرض الإدارة على مقاول الأشغال العامة إختيار مواد معينة. أثره.…
- حق المتعاقد في الامتناع عن الوفاء بالتزامه إذا لم يقم المتعاقد الآخر بالوفاء بما التزم به. قاعدة عامة تطبق على…
- تأخر المقاول في تنفيذ العقد لا يدل بذاته على تحمله غرامة تأخير.…
- المقاول ملزم بتنفيذ العمل طبقاً لشروط عقد المقاولة. قيام أو عدم قيام المقاول بإنجاز العمل على هذا النحو واقعة …
- رجوع مقاول الباطن على رب العمل. شرطه. أن يكون رب العمل مديناً للمقاول الأصلي.…