Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 2416

State of Kuwait · Pleadings — Part Two · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

The general rule is that no direct relationship exists between the employer and the subcontractor. The latter may claim from the employer what the employer owes to the principal contractor by an indirect action. Exception. The subcontractor has a direct action against the employer and a preferential right over the sums due to the principal contractor. Its effect. From the date the action is brought, the employer is prohibited from paying the principal contractor. - Transfer of the principal contractor’s right against the employer to the assignee occurs subject to the preferential right prescribed by law for the subcontractor, where the assignment takes place on a date subsequent to the conclusion of the subcontract. - 454 - Civil Procedure
Arabic original
الأصل عدم قيام علاقة مباشرة بين رب العمل والمقاول من الباطن. للأخير مطالبة رب العمل بما هو مستحق من ذمته للمقاول الأصلي بالدعوى غير المباشرة. الاستثناء. له قبله دعوى مباشرة وحق امتياز على المبالغ المستحقة للمقاول الأصلي. أثرها. يمتنع على رب العمل من تاريخ رفعها الوفاء للمقاول الأصلي. - انتقال حق المقاول الأصلي قبل رب العمل إلى المحال له يتم مثقلاً بالامتياز المقرر قانوناً للمقاول من الباطن. متى تمت الحوالة في تاريخ لاحق لإبرام عقد المقاولة من الباطن. - ٤٥٤ - المرافعات
Original Arabic judgment citations

(الطعن ٣١٤/١٩٩٠ تجاري جلسة ١١/٥/١٩٩٢ مج القسم الثالث المجلد الثاني ص٩٢٤)

Source: Court of Cassation legal principles collection — Pleadings — Part Two — Ministry of Justice — Court of Cassation — Technical Office. Printed page 454. PDF pages: 451.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace