Kuwait Court of Cassation principle number 2376
State of Kuwait · Commercial and Labour — Volume 9 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
Delay penalties in contracts for work. Considered a form of penalty clause or agreed compensation. The implication thereof. Their subjection to the control of the court of fact as to entitlement and assessment.
Arabic original
غرامات التأخير في مجال عقود المقاولات. اعتبارها من قبيل الشرط الجزائي أو التعويض الاتفاقي. مؤدى ذلك. خضوعها لهيمنة محكمة الموضوع استحقاقاً وتقديراً.Original Arabic judgment citations
(الطعن ١٧٤/٢٠٠٣ تجاري جلسة ٢٤/٣/٢٠٠٤ مج القسم الخامس - المجلد الثامن ص ٥١)
Source: Court of Cassation legal principles collection — Commercial and Labour — Volume 9 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 410. PDF pages: 410.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- حرية المتعاقدين في تعديل أحكام المسئولية العقدية التي أنشأتها إرادتهما الحرة في حدود القانون وقواعد النظام الع…
- التعويض الإتفاقي هو شرط جزائي إذا لم يكن محل الالتزام مبلغاً من النقود. - الدفع ببطلان الشرط الجزائي لقبول الم…
- غرامة التأخير. عدم استحقاقها إذا أثبت المدين أنه لم يرتكب خطأ أو أن الدائن لم يلحقه ضرر علة ذلك أنها من قبيل ا…
- الشرط الجزائي. التزام تابع لالتزام أصلي. أثر سقوطه. عدم الإعتداد بالتعويض المقدر بمقتضاه. أثر تحقيقه. تولد تعو…
- اقتصار الشرط الجزائي على الالتزام الذي لا يكون محله مبلغاً من النقود. علة ذلك.…
- وجود الشرط الجزائي في العقد يوجب على القاضي إعماله. إذا أثبت المدين أن الدائن لم يلحقه ضرر. لا يستحق التعويض. …