Kuwait Court of Cassation principle number 2419
State of Kuwait · Civil Matters — Volume 10 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
Delay penalties in works contracts. Their treatment as a penalty clause or agreed compensation. The implication thereof. Their subjection to the trial court’s control as to entitlement and assessment.
Arabic original
غرامات التأخير في مجال عقود المقاولا ت. اعتبارها من قبيل الشرط الجزائي أو التعويض الاتفاقى. مؤدى ذلك. خضوعها لهيمنة محكمة الموضوع استحقاقاً وتقديراً.Original Arabic judgment citations
(الطعن ١٧٤/٢٠٠٣ تجاري جلسة ٢٤/٣/٢٠٠٤ مج القسم الخامس - المجلد الثامن ص ٦٦٩)
Source: Court of Cassation legal principles collection — Civil Matters — Volume 10 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 447. PDF pages: 447.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- عقد الإيجار محدد المدة. تضمنه شرط التنبيه بالانتهاء في ميعاد معين. مفاده. ضرورة الإخطار في الميعاد. مخالفة ذلك…
- قرينة افتراض حصول ضرر مساو لما قدره العاقدان مقدماً من تعويض عند تحقق الشرط الجزائي. جواز نفي المدين لها بإثبا…
- الجزاء المالي الذي يفرضه المتعاقدان. ماهيته: شرط جزائي أو تعويض اتفاقي. الهدف منه. جبر الضرر الذي يصيب المتعاق…
- غرامة التأخير. عدم استحقاقها إذا أثبت المدين أنه لم يرتكب خطأ أو أن الدائن لم يلحق ضرر. علة ذلك. أنها من قبيل …
- الاتفاق على التعويض بموجب شرط جزائي بالعقد. مؤداه. أن الضرر مفترض لا يكلف الدائن بإثباته. إذا ادعى المدين عدم …
- وجود الشرط الجزائي. مؤداه: أن تقدير التعويض مناسب مع الضرر. أثره: أن على القاضي إعماله. متى يجوز للقاضي تخفيضه…