Kuwait Court of Cassation principle number 4109
State of Kuwait · Civil Matters — Volume 10 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
Delay penalties in contracts for work. Considered a form of penalty clause or agreed compensation. The implication thereof. Their subjection to the control of the court of fact as to entitlement and assessment.
Arabic original
غرامات التأخير في مجال عقود المقاولات. اعتبارها من قبيل الشرط الجزائي أو التعويض الاتفاقي. مؤدى ذلك. خضوعها لهيمنة محكمة الموضوع استحقاقاً وتقديراً.Original Arabic judgment citations
(الطعن ١٧٤/٢٠٠٣ تجاري جلسة ٢٤/٣/٢٠٠٤ مج القسم الخامس - المجلد الرابع ص ٤١٥)
Source: Court of Cassation legal principles collection — Civil Matters — Volume 10 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 758. PDF pages: 758.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- الجزاء المالي الذي يفرضه المتعاقدان. ماهيته: شرط جزائي أو تعويض اتفاقي. الهدف منه. جبر الضرر الذي يصيب المتعاق…
- قرينة افتراض حصول ضرر مساوٍ لما قدره العاقدان مقدماً من تعويض عند تحقق الشرط الجزائي. جواز نفي المدين لها بإثب…
- اتفاق المتعاقدين مقدماً على مقدار التعويض المستحق للدائن عن إخلال المدين بالتزامه. افتراض حصول ضرر مساوٍ لما ق…
- حق الإدارة في توقيع الجزاءات المالية أثناء تنفيذ العقد عن إخلال الطرف الآخر بالتزاماته استنفاد - ٧٥٤ - التزام …
- الاتفاق على التعويض بموجب شرط جزائي بالعقد. مؤداه. أن الضرر مفترض لا يكلف الدائن بإثباته. إذا ادعى المدين عدم …
- وجود الشرط الجزائي. مؤداه: أن تقدير التعويض متناسب مع الضرر. أثره. على القاضي أعماله. متى يجوز للقاضي تخفيضه.…