Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 1430

State of Kuwait · Civil Matters — Volume 11 · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

The general rule is the absence of a direct relationship between the employer and the subcontractor. The latter may claim from him, through an indirect action, what he owes to the principal contractor. The exception. He has a direct action against him and a preferential right over the sums due to the principal contractor. Its effect. From the date it is filed, the principal contractor is precluded from making payment to the principal contractor. - Transfer of the principal contractor’s right against the employer to the assignee takes place encumbered by the preferential right established by law for the subcontractor, where the assignment occurs on a date subsequent to conclusion of the subcontract. - 270 - Obligation
Arabic original
الأصل عدم قيام علاقة مباشرة بين رب العمل والمقاول من الباطن. للأخير مطالبته بما هو مستحق في ذمته للمقاول الأصلي بالدعوى غير المباشرة. الاستثناء.له قبله دعوى المباشرة وحق امتياز على المبالغ المستحقة للمقاول الأصلي. أثرها. يمتنع على المقاول الأصلي من تاريخ رفعها الوفاء للمقاول الأصلي. - انتقال حق المقاول الأصلي قبل رب العمل إلى المحال له يتم مثقلاً بالامتياز المقرر قانوناً للمقاول من الباطن. متى تمت الحوالة في تاريخ لاحق لإبرام عقد المقاولة من الباطن. - ٢٧٠ - التزام
Original Arabic judgment citations

(الطعن ٣١٤/١٩٩٠ تجاري جلسة ١١/٥/١٩٩٢ مج القسم الثالث - المجلد الثالث ص ٧٢٤)

Source: Court of Cassation legal principles collection — Civil Matters — Volume 11 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 270. PDF pages: 270.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace