Kuwait Court of Cassation principle number 1958
State of Kuwait · Civil Matters — Volume 11 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
Impossibility of performance due to force majeure resulting in automatic dissolution of the contract and extinction of the obligations arising from it. Its scope. That the contract be in existence at the time the extraneous cause occurs.
Arabic original
استحالة التنفيذ بسبب القوة القاهرة الذي يترتب عليها انفساخ العقد من تلقاء نفسه وانقضاء الالتزامات الناشئة عنه. مجاله. أن يكون العقد قائماً في وقت وقوع السبب الأجنبي.Original Arabic judgment citations
(الطعن ٣٤/٩٤ عمالي جلسة ١/٥/١٩٩٥ مج القسم الثالث - المجلد الأول ص ٧٢٠)
Source: Court of Cassation legal principles collection — Civil Matters — Volume 11 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 372. PDF pages: 372.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- الإبراء. هو تصرف تبرعي محض من جانب الدائن تسري عليه أحكام التبرع. أساس ذلك. - ركن السبب في التبرعات. العبرة في…
- عدم تنفيذ الالتزام يرتب في ذمة المدين نوعين من التعويض. تعويض عن عدم التنفيذ وتعويض عن التأخير في التنفيذ. إذا…
- استخلاص استحالة تنفيذ الالتزام استحالة فعلية أو عدم استحالته. من سلطة محكمة الموضوع.…
- استحالة التنفيذ التي يترتب عليها انقضاء الالتزام. قد تكون فعلية أو قانونية. الاستحالة الفعلية. واقع.…
- الإستحالة الفعلية لتنفيذ الالتزام بالرد. استخلاصها. من سلطة محكمة الموضوع.…
- هلاك العين المؤجرة هلاكاً كلياً أثناء المدة المطالب بأجرتها لسبب لا يد لأحد المتعاقدين فيه. مؤداه. انفساخ عقد …