Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 3463

State of Kuwait · Civil Matters — Volume 11 · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

An increase or decrease in the costs of the work. It has no effect on the extent of the obligations arising from the contract for work: it is not permissible—682—Contract for Work—for the contractor, when costs increase, to demand an increase in the consideration, nor is it permissible for the employer, when costs decrease, to demand a reduction in the consideration. Its condition. Without prejudice to the provisions of the theory of unforeseen circumstances. - The contractor's obligation, if factors arise during the execution of the work that would impede execution, to notify the employer immediately; otherwise, the contractor is liable for everything resulting therefrom.
Arabic original
ارتفاع تكاليف العمل أو انخفاضها. لا أثر لها في مدى الالتزامات التي يرتبها عقد المقاولة: لا يجوز - 682 - مقاولة للمقاول عند ارتفاع التكاليف المطالبة بزيادة في المقابل ولا يجوز لصاحب العمل عند انخفاض التكاليف المطالبة بإنقاص المقابل. شرطه. عدم الإخلال بأحكام نظرية الظروف الطارئة. - التزام المقاول إذا قامت عوامل أثناء تنفيذ العمل من شأنها أن تعوق التنفيذ بإخطار رب العمل فوراً وإلا كان مسئولاً عن كل ما يترتب على ذلك.
Original Arabic judgment citations

(الطعن ٢٢٥/٩٠ تجاري جلسة ١٥/٣/١٩٩٢ مج القسم الثالث - المجلد الثالث ص ٩٤٢)

Source: Court of Cassation legal principles collection — Civil Matters — Volume 11 — Ministry of Justice — Court of Cassation — Technical Office. PDF pages: 682–683.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace