Delay penalty. Its definition. An agreed penalty clause subject to the trial court’s assessment as to entitlement and amount. - Absence of the contractor’s liability. Its condition. - 377 - Commercial
Arabic original
غرامة التأخير. تعريفها. شرط جزائي اتفاقي يخضع لتقدير محكمة الموضوع استحقاقاً وتقديراً. - انتفاء مسئولية المقاول. شرطها. - ٣٧٧ - تجاري
Original Arabic judgment citations

(الطعن ٢٨٤/١٩٩٠ تجاري جلسة ٩/٣/١٩٩٢ مج القسم الثالث - المجلد الثالث ص ٩٤٢)

Source: Court of Cassation legal principles collection — Commercial and Labour — Volume 9 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 377. PDF pages: 377.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace