Kuwait Court of Cassation principle number 2170
State of Kuwait · Commercial and Labour — Volume 9 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
Delay penalty. Its definition. An agreed penalty clause subject to the trial court’s assessment as to entitlement and amount. - Absence of the contractor’s liability. Its condition. - 377 - Commercial
Arabic original
غرامة التأخير. تعريفها. شرط جزائي اتفاقي يخضع لتقدير محكمة الموضوع استحقاقاً وتقديراً. - انتفاء مسئولية المقاول. شرطها. - ٣٧٧ - تجاريOriginal Arabic judgment citations
(الطعن ٢٨٤/١٩٩٠ تجاري جلسة ٩/٣/١٩٩٢ مج القسم الثالث - المجلد الثالث ص ٩٤٢)
Source: Court of Cassation legal principles collection — Commercial and Labour — Volume 9 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 377. PDF pages: 377.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- الوفاء بالدين. تمامه بقيام المدين مباشرة بإيداعه أو اتخاذه الإجراء البديل عن الإيداع وفقاً لأحكام قانون المراف…
- فرض الإدارة على مقاول الأشغال العامة إختيار مواد معينة أثره.…
- مقاول التفريغ تابع للسفينة ويُسأل الناقل عن أخطائه قبِلَ المرسل إليه. امتناع رجوع المرسل إليه عقدياً عليه. - ٣…
- حق المتعاقد في الامتناع عن الوفاء بإلتزامه إذا لم يقم المتعاقد الآخر بالوفاء بما التزم به. قاعدة عامة تطبق على…
- تأخر المقاول في تنفيذ العقد لا يدل بذاته على تحمله غرامة تأخير.…
- أجرة النقل البحري. المختصون بتحصيلها. وكيل السفينة ومقاول الشحن والتفريع ووكيل الحمولة.…