Kuwait Court of Cassation principle number 2190
State of Kuwait · Commercial and Labour — Volume 9 · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
Determining the existence or absence of fault on the part of the employer or the main contractor in his capacity as employer, by which the contractor's liability for delay in performance is excluded. Within the authority of the court of merits. The condition therefor. Example.
Arabic original
استخلاص توافر خطأ رب العمل أو المقاول الأصلي بوصفه رب عمل الذي تندفع به مسئولية المقاول عن التأخير في التنفيذ أو نفيه. من سلطة محكمة الموضوع. شرط ذلك. مثال.Original Arabic judgment citations
(الطعن ٣٠٦/١٩٩٥ تجاري جلسة ١٠/٣/١٩٩٧ مج القسم الرابع - المجلد السادس ص ٥٢٠)
Source: Court of Cassation legal principles collection — Commercial and Labour — Volume 9 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 380. PDF pages: 380.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- الوفاء بالدين. تمامه بقيام المدين مباشرة بإيداعه أو اتخاذه الإجراء البديل عن الإيداع وفقاً لأحكام قانون المراف…
- فرض الإدارة على مقاول الأشغال العامة إختيار مواد معينة أثره.…
- مقاول التفريغ تابع للسفينة ويُسأل الناقل عن أخطائه قبِلَ المرسل إليه. امتناع رجوع المرسل إليه عقدياً عليه. - ٣…
- حق المتعاقد في الامتناع عن الوفاء بإلتزامه إذا لم يقم المتعاقد الآخر بالوفاء بما التزم به. قاعدة عامة تطبق على…
- تأخر المقاول في تنفيذ العقد لا يدل بذاته على تحمله غرامة تأخير.…
- أجرة النقل البحري. المختصون بتحصيلها. وكيل السفينة ومقاول الشحن والتفريع ووكيل الحمولة.…