Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 2208

State of Kuwait · Commercial and Labour — Volume 9 · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

The employer and subcontractor. No contractual relationship binds them. The latter may claim from the former the amount he owes to the main contractor by an indirect action. He also has a direct action and a preferential right against him to spare him competition with the main contractor’s creditors. Articles 682, 683, Civil Code. The condition for this. The employer’s debt to the main contractor must arise from the contract for works, and upon the action being brought he is barred from paying the main contractor.
Arabic original
صاحب العمل والمقاولمنالباطن. لايربطهما أي تعاقد. للثانيأن يطالب الأول بما هومستحق في ذمته للمقاول الأصلي بدعوى غير مباشرة. وله دعوى مباشرة وحق امتياز قبله لتجنيبه مزاحمة دائني المقاول الأصلي. م ٦٨٢، ٦٨٣ مدني. شرط ذلك. أن يكون دين رب العمل للمقاول الأصلي ناشئاً عن عقد المقاولة وبرفع الدعوى يمتنع عليه الوفاء للمقاول الأصلي.
Original Arabic judgment citations

(الطعن ١١/٢٠٠٣ تجاري جلسة ٤/٣/٢٠٠٦ مج القسم الخامس - المجلد الحادي عشر ص ٢٠٥)

Source: Court of Cassation legal principles collection — Commercial and Labour — Volume 9 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 383. PDF pages: 383.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace