Judicial principle — Kuwait Court of Cassation

Kuwait Court of Cassation principle number 3496

State of Kuwait · Civil Matters — Volume 11 · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

The employer and the subcontractor. No contract binds them. The latter may claim from the former what he owes to the main contractor by an indirect action. He also has a direct action and a preferential right against him to spare him competition with - 688 - Contract for works the main contractor's creditors. Articles 682, 683, Civil Code. The condition for this. That the employer's debt to the main contractor arise from the contract for works; upon the action being brought, he is precluded from paying the main contractor.
Arabic original
صاحب العمل والمقاول من الباطن. لا يربطهما أي تعاقد. للثاني أن يطالب الأول بما هو مستحق في ذمته للمقاول الأصلي بدعوى غير مباشرة. وله دعوى مباشرة وحق امتياز قبله لتجنيبه مزاحمة - 688 - مقاولة دائني المقاول الأصلي. م ٦٨٢، ٦٨٣ مدني. شرط ذلك. أن يكون دين رب العمل للمقاول الأصلي ناشئاً عن عقد المقاولة وبرفع الدعوى يمتنع عليه الوفاء للمقاول الأصلي.
Original Arabic judgment citations

(الطعن ١١/٢٠٠٣ تجاري جلسة ٤/٣/٢٠٠٦ مج القسم الخامس - المجلد الحادي عشر ص ٢٠٥)

Source: Court of Cassation legal principles collection — Civil Matters — Volume 11 — Ministry of Justice — Court of Cassation — Technical Office. PDF pages: 688–689.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace