The prerequisite for applying the doctrine of unforeseen circumstances is that the delay in performance of the obligation until after the unforeseen event occurred must not be attributable to the debtor's fault. The reason for that. Example.
Arabic original
مناط إعمال نظرية الظروف الطارئة هو ألاّ يكون تراخي تنفيذ الالتزام إلى مابعد وقوع الحادث الطارئ راجعاً إلى خطأ المدين. علة ذلك. مثال.Original Arabic judgment citations
(الطعن ٢٢٥/١٩٩٨ تجاري جلسة ٢١/١٠/١٩٩٨ مج القسم الرابع - المجلد الخامس ص ٣٠٧)
Source: Court of Cassation legal principles collection — Commercial and Labour — Volume 9 — Ministry of Justice — Court of Cassation — Technical Office. Printed page 408. PDF pages: 408.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- الدفع بعدم تنفيذ الالتزام. شرطه. تقصير المتعاقد الآخر في التزام مقابل له ومرتبط به سواء كان الارتباط بنص في ال…
- الظرف الطارئ الذي من شأنه الإخلال باقتصاديات العقد. ما يكفي لتوافره.…
- نظرية الظروف الطارئة. شرط اعمالها. حدوث خسارة فادحة للمتعاقد تخرج عن الحد المألوف من شأنها الإخلال باقتصاديات …
- نظرية الظروف الطارئة. شروط إعمالها. ضرورة تنفيذ التزام المدين مرهقاً بسبب الحادث الطارئ بحيث يسبب له خسارة فاد…
- ارتفاع تكاليف العمل أو انخفاضها لا أثر لها في مدى الالتزامات التي يرتبها عقد المقاولة. لا يجوز للمقاول عند ارت…
- القوة القاهرة التي تحل خلال الفترة المحددة لتنفيذ الالتزام. اعتبارها من الظروف الطارئة التي تجعل التنفيذ مستحي…