Kuwait Court of Cassation principle number 2393
State of Kuwait · Pleadings — Part Two · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
The subcontractor has a direct action against the employer for what is due to him from the principal contractor. The condition therefor. That the employer owes a debt to the principal contractor arising from the contract for works.
Arabic original
للمقاول من الباطن دعوى مباشرة قبل رب العمل بما هو مستحق له قبل المقاول الأصلي. شرط ذلك. أن تكون ذمة رب العمل مشغولة بدين للمقاول الأصلي ناشئاً عن عقد المقاولة.Original Arabic judgment citations
(الطعنان ٣٨، ٤٠/١٩٩٤ تجاري جلسة ٤/١٢/١٩٩٤ مج القسم الثالث المجلد الأول ص٩٢٢)
Source: Court of Cassation legal principles collection — Pleadings — Part Two — Ministry of Justice — Court of Cassation — Technical Office. Printed page 450. PDF pages: 447.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- الدعوى الفرعية. ارتباطها بالدعوى الأصلية. تبقى ببقائها وتزول بزوالها. صدور حكم في الدعوى الأصلية بعدم اختصاص ا…
- التأمين عن المسئولية المدنية عن حوادث السيارات إجباري لصالح الغير الذي يحل به الضرر في نفسه أو ماله ويخول للمض…
- الأصل عدم قيام علاقة مباشرة بين رب العمل والمقاول من الباطن. للأخير مطالبة رب العمل بما هو مستحق في ذمته للمقا…
- تحمل المتعاقد عن نفسه بالتزامات معينة يتعهد بأدائها لشخص من الغير. جائز. جواز أن يكون هذا الشخص غير معين بالذا…
- الدعوى المباشرة وحق الامتياز المقررين لمقاول الباطن تجاه المقاول الأصلي. حدودهما: ما يكون للمقاول الأصلي لدى ر…
- تحديد شرط السرعة والسير عكس الاتجاه وتجاوز الإشارة الضوئية بما يخول المؤمن الرجوع على المؤمن له. اعتبارها من ا…