Kuwait Court of Cassation principle number 2399
State of Kuwait · Pleadings — Part Two · Ministry of Justice — Court of Cassation — Technical Office
English translation of the principle
The subcontractor's workers have the right to bring a direct claim against the main contractor for what is owed to them by the subcontractor. The condition for this: that the main contractor owes a debt to the subcontractor.
Arabic original
لعمال المقاول من الباطن حق الادعاء المباشر قبل المقاول الأصلي بما يستحق لهم قبل المقاول من الباطن. شرط ذلك: أن تكون ذمة المقاول الأصلي مشغولة بدين للمقاول من الباطن.Original Arabic judgment citations
(الطعن ٦١/١٩٩٨ عمالي جلسة ١١/١/١٩٩٩ مج القسم الرابع المجلد الرابع ص٧٣٢)
Source: Court of Cassation legal principles collection — Pleadings — Part Two — Ministry of Justice — Court of Cassation — Technical Office. Printed page 451. PDF pages: 448.
Ask the assistant about this principle
Guidance based on the principle and its source details, separate from the original collection text.
Related principles
- الدعوى الفرعية. ارتباطها بالدعوى الأصلية. تبقى ببقائها وتزول بزوالها. صدور حكم في الدعوى الأصلية بعدم اختصاص ا…
- التأمين عن المسئولية المدنية عن حوادث السيارات إجباري لصالح الغير الذي يحل به الضرر في نفسه أو ماله ويخول للمض…
- الأصل عدم قيام علاقة مباشرة بين رب العمل والمقاول من الباطن. للأخير مطالبة رب العمل بما هو مستحق في ذمته للمقا…
- تحمل المتعاقد عن نفسه بالتزامات معينة يتعهد بأدائها لشخص من الغير. جائز. جواز أن يكون هذا الشخص غير معين بالذا…
- للمقاول من الباطن دعوى مباشرة قبل رب العمل بما هو مستحق له قبل المقاول الأصلي. شرط ذلك. أن تكون ذمة رب العمل م…
- الدعوى المباشرة وحق الامتياز المقررين لمقاول الباطن تجاه المقاول الأصلي. حدودهما: ما يكون للمقاول الأصلي لدى ر…