Kuwait Court of Cassation principle number 2413

State of Kuwait · Pleadings — Part Two · Ministry of Justice — Court of Cassation — Technical Office

English translation of the principle

The employer and the subcontractor. No contractual relationship links them. The effect thereof. The second may claim from the first what the first owes the main contractor by an indirect action. He also has a direct action and a preferential right against him to spare him competition from the main contractor's creditors. Articles 682, 683, Civil Code. The condition thereof. The employer's debt to the main contractor must arise from the contract for works, and upon the action being brought he is precluded from paying the main contractor.
Arabic original
صاحب العمل والمقاول من الباطن. لا يربطهما أي تعاقد. أثر ذلك. للثاني أن يطالب الأول بما هو مستحق في ذمته للمقاول الأصلي بدعوى غير مباشرة. وله دعوى مباشرة وحق امتياز قبله لتجنيبه مزاحمة دائني المقاول الأصلي. م٦٨٢، ٦٨٣ مدني. شرط ذلك. أن يكون دين رب العمل للمقاول الأصلي ناشئاً عن عقد المقاولة وبرفع الدعوى يمتنع عليه الوفاء للمقاول الأصلي.
Original Arabic judgment citations

(الطعن ١١/٢٠٠٣ تجاري جلسة ٤/٣/٢٠٠٦ مج القسم الخامس المجلد السابع ص٣٢٢)

Source: Court of Cassation legal principles collection — Pleadings — Part Two — Ministry of Justice — Court of Cassation — Technical Office. Printed page 454. PDF pages: 451.

Ask the assistant about this principle

Guidance based on the principle and its source details, separate from the original collection text.

Related principles

Continue your case in the legal workspace

Open legal workspace